Dear Michael,
Further to my last mail sent to you yesterday. We have been informed by Khun Chit that
there are many more items that you would like to change from the standard category of our original design.
Some of those items, i.e. toilet brand and accessories which are hard to find the price and may not be available timely.
The special floor tile that you chose is expensive and hard to find our existing contractor to pave them.
We may have to cut those items out from our task list and let Khun Chit finds the contractor to handle them.
Please concur that those alterations will prolong Nirvana's completion of the main house as contractual agreement (ending July 2014) !
We will try our best to summarize those items before our meeting of July 24th, hopefully !
Regards,