At the moment Mr Deepak, my senior performance and investment manager, is discussing with Mr Hans to finalize the commissioning schedule. I got that it will be in this week. Whenever I had final commissioning schedule.
Regarding the mill capacity after the mill restarted, until now due to issue regarding the kiln operation issue so blending silo is almost full, we run low capacity of raw mill just to correct the chemical properties of kiln feed.
During operation trial, some points could be shared with you:
- Mill capacity: it could be achieved 355-360 tph but I couldn't maintain for long time. Now the kiln is normal operation so on Wednesday this week I will run maximum capacity to check
- Mill delta P: it looks better than before nozzle ring modification (reduced about 6 mbar)
- Mill fan: trialing dampers control, I will confirm the fan performance after maximize capacity on Wednesday and Thursday this week
- Reject: stable at 9-10 kW of reject bucket elevators, a little bit higher before modification (5-6 kW)
I could say that until now I observed good result on mill delta P, fan reserve and mill capacity will be informed this week.
At the moment Mr Deepak, my senior performance and investment manager, is discussing with Mr Hans to finalize the commissioning schedule. I got that it will be in this week. Whenever I had final commissioning schedule.Regarding the mill capacity after the mill restarted, until now due to issue regarding the kiln operation issue so blending silo is almost full, we run low capacity of raw mill just to correct the chemical properties of kiln feed.During operation trial, some points could be shared with you:- Mill capacity: it could be achieved 355-360 tph but I couldn't maintain for long time. Now the kiln is normal operation so on Wednesday this week I will run maximum capacity to check- Mill delta P: it looks better than before nozzle ring modification (reduced about 6 mbar)- Mill fan: trialing dampers control, I will confirm the fan performance after maximize capacity on Wednesday and Thursday this week- Reject: stable at 9-10 kW of reject bucket elevators, a little bit higher before modification (5-6 kW)I could say that until now I observed good result on mill delta P, fan reserve and mill capacity will be informed this week.