Dear Khun Worapoj ,
Now J 326 under shutdown period. The overall progress are delay from master plan due to the plant operation unable to release line system to QTEC for tie-in.
In this regards is directly impact with our demobilize plan as following;
- Mr. Worawit Mahamitr Planner engineer postpone to end of July 2015
- Mr. Jarupat Thongsupim Supervisor postpone to end of July 2015
Please kindly inform to ESSO in advance to avoid any complain from them.
Regards
Preechapol d.