July 2010 - December 2011
Owner : PTT Tank Terminal Co., Ltd.
Project : Ammonia Storage Tank and Facilities Project.
Position : QC Inspector
Responsibility : Field erection inspection of the pipe line.
The inspection was carried out such as welds visual inspection, test, hydrostatic test.