K Plant Constuction Phase 2 Somsak
28/6/16
Minue of Meeting Answer In Charge Due date Progress
1) Need Quotation O
- Rental term - 8years or 5.5years 8years Somsak
- Base construction + 3 Roofs (Between Phase1 & Phase2) End June
- SPC Materials receiving yard, F/G shipping yard)
2) Other Investment O
- Decide within July (Invested by Owner or by SEWT) STS Somsak End June
3) Report to SWS & Approval by SWS
- Need to report on Jomukai(Executive Board meeting) Jun.27th - Mr.Ishida VP
Construction Remain Item In Charge Due date Progress
1) Ventilation systems (Air Blow ) Standard 32 C ( 800 Persons)
- Government Regulation Law Application / Audit STS
1.1 อบต. Sub district Administrative Organization (SAO) STS Sep'16
1.2 โยธา Department of Public Works and Town & Country Planning STS
1.3 อุตสาหกกรม Provincial Industrial Officer SEWT
2) Roof Phase 1 - 2 ( Application Same Building)
-Application & Audit STS Sep'16
3)Electrical Power /Load & Capacity Check Somsak
-Electrical Data Locker Monotoring (Thaisemcon ) TSC 15th Jul
4)Addition Shipping Yard Springer Systems STS
Aug'16
5)Office Lay out SEWT
SPC 15th Jul