9.Instructions
(i)The Contractor shall comply with the instructions of the Project Manager at all times.
(ii)If the Contractor fails to carry out any obligation under the Contract, the
Project Manager may by notice require the Contractor to make good the failure and to remedy it within a specified reasonable time.
9.1Project Managers Determinations
Whenever these Conditions provide that the Project Manager shall agree or determine any matter, the Project Manager shall consult with each Party in an endeavour to reach agreement. If agreement is not achieved, the Project Manager shall make a fair determination in accordance with the Contract, taking due regard of all relevant circumstances.
The Project Manager shall give notice to both Parties of each agreement or determination, with supporting particulars. Each Party shall give effect to each agreement or determination unless and until revised under Clause 24.