When construction requires to shut down electric power of high-voltage and extra-high-voltage equipment,
S/M shall complete and submit a “Power interruption construction work procedure plan” (Format XXX)
Project owner shall cooperate and notify organizational units (owner company (maintenance or utility))
that controll the electric power in advance for shut down electric power