Dear K.Anukul,
Per our discussion on Feb 13 ‘2016.
The summarize as below:
1. Fujikura confirm the current order will follow Rev. 0 or 495V836.
1.1 Existing tooling, advance metal is already complete to modify to Rev.A
1.2 Fujikura is request to Advance metal to modify that tooling again > Back to Rev.0.
*** By change the die insert part and punch. Lead time 3 days.
1.3 Modication cost, Fujikura will paid.
2. Fujikura need the part 495V836 Rev.0 within this week.
*** Partial shipment is OK.
3. After complete this current order quantity, 495V836 Rev.0
*** Next lot order is follow new 495V836 Rev.A, order quantity ~ 3,600 pcs.
Let’s help to follow as above summarize,.
Any comment, please let me know.
Thank you very much for your support.
BR,
Niwat