Reference is made to KT‘s submittal letter requesting PCGRN to review the adjustment of the Civil Works Contract in Depot and OCC.
PCGRN have reviewed your sketch design, found that there are some items proposed by KT to change the civil works contract and will cause the time and cost impact. PCGRN request KT to formally resubmit the relevant change request to PCGRN together with the modified Design Drawings and stating the reasons for the need to change (individually item) with affected the cost and time proposal for PCGRN’s consideration before submit to MRTA for approval.
PCGRN kindly ask KT to submit all relevant necessary requests with detailed justification for Depot and OCC through formal letter soonest as the construction is processing.
Your kind acknowledgement and prompt further action would be highly appreciated.