Except for items expressly required to be provided by Contractor pursuant to Exhibit 1, Subcontractor shall provide all necessary Equipments and Permanent Materials, Construction Equipment, Services, supplies, utilities, and fuel required for the performance of the Work. All procurement shall be accomplished in accordance with the provisions of this Contract. All costs of any kind and all delay in or disruption to the Work Schedule incurred as a result of Contractor's rejection of Equipment and Materials not conforming with the requirements of this Contract shall be borne by Subcontractor.