COMPANY Raiwin Maintenance &Service Co.,Ltd.
POSITION Electrical engineer
COMPANY: Raiwin Maintenance &Service Co.,Ltd.
DURATION: Oct 2012-Dec 2012
PROJECT : Bang pa-in cogeneration project 1(Control and Instrument Work) 
CUSTOMER/CLIENT: Thai shinryo Limited
POSITION: engineer
RESPONSIBILITY: -Project Planning ,Progress S-Curve,3-Weekly schedule,Daily report
 -Document Control
 -Project Control
 -Contract Supplier
 -Material Take Off for Project 
-QA/QC Inspector and document report
 Inspection
 Insulation Resistance & Continuity Test
 Loop Test
 -Shop Drawing
 
COMPANY: Raiwin Maintenance &Service Co.,Ltd.
POSITION : Electrical engineer
COMPANY : Raiwin Maintenance &Service Co.,Ltd.
DURATION : May 2012-Dec 2012
PROJECT : Bang pa-in cogeneration project 1(115KV/22KV Electrical Installation Work)
CUSTOMER/CLIENT: Thai shinryo Limited
POSITION: Electeical engineer
RESPONSIBILITY : -Project Planning ,Progress S-Curve,3-Weekly schedule,Daily report
 -Document Control
 -Project Control
 -Contract Supplier
 -Material Take Off for Project 
-QA/QC Inspector and document report
 
COMPANY Raiwin Maintenance &Service Co.,Ltd.
POSITION Electrical engineer
COMPANY: Raiwin Maintenance &Service Co.,Ltd.
DURATION: Oct 2012-Dec 2012
PROJECT : Bang pa-in cogeneration project 1(Control and Instrument Work) 
CUSTOMER/CLIENT: Thai shinryo Limited
POSITION: engineer
RESPONSIBILITY: -Project Planning ,Progress S-Curve,3-Weekly schedule,Daily report
 -Document Control
 -Project Control
 -Contract Supplier
 -Material Take Off for Project 
-QA/QC Inspector and document report
 Inspection
 Insulation Resistance & Continuity Test
 Loop Test
 -Shop Drawing
 
COMPANY: Raiwin Maintenance &Service Co.,Ltd.
POSITION : Electrical engineer
COMPANY : Raiwin Maintenance &Service Co.,Ltd.
DURATION : May 2012-Dec 2012
PROJECT : Bang pa-in cogeneration project 1(115KV/22KV Electrical Installation Work)
CUSTOMER/CLIENT: Thai shinryo Limited
POSITION: Electeical engineer
RESPONSIBILITY : -Project Planning ,Progress S-Curve,3-Weekly schedule,Daily report
 -Document Control
 -Project Control
 -Contract Supplier
 -Material Take Off for Project 
-QA/QC Inspector and document report
การแปล กรุณารอสักครู่..

 
 
 
COMPANY Raiwin Maintenance &Service Co.,Ltd.
POSITION Electrical engineer
COMPANY: Raiwin Maintenance &Service Co.,Ltd.
DURATION: Oct 2012-Dec 2012
PROJECT : Bang pa-in cogeneration project 1(Control and Instrument Work) 
CUSTOMER/CLIENT: Thai shinryo Limited
POSITION: engineer
RESPONSIBILITY: -Project Planning ,Progress S-Curve,3-Weekly schedule,Daily report
 -Document Control
 -Project Control
 -Contract Supplier
 -Material Take Off for Project 
-QA/QC Inspector and document report
 Inspection
 Insulation Resistance & Continuity Test
 Loop Test
 -Shop Drawing
 
COMPANY: Raiwin Maintenance &Service Co.,Ltd.
POSITION : Electrical engineer
COMPANY : Raiwin Maintenance &Service Co.,Ltd.
DURATION : May 2012-Dec 2012
PROJECT : Bang pa-in cogeneration project 1(115KV/22KV Electrical Installation Work)
CUSTOMER/CLIENT: Thai shinryo Limited
POSITION: Electeical engineer
RESPONSIBILITY : -Project Planning ,Progress S-Curve,3-Weekly schedule,Daily report
 -Document Control
 -Project Control
 -Contract Supplier
 -Material Take Off for Project 
-QA/QC Inspector and document report
การแปล กรุณารอสักครู่..

 
 
 
บริษัทไรวินท์การบำรุงรักษา& Service Co . , Ltd . 
 
 ตำแหน่งวิศวกรไฟฟ้า 
 บริษัท : บริษัท ไรวินท์ ซ่อมบำรุง& Service Co . , Ltd . 
 
 ระยะเวลา ต.ค. ธ.ค. 
 
 โครงการ : บางป่าในโครงการผลิตไฟฟ้า 1 ( ควบคุมงานเรียบเรียง ) 
 
 ลูกค้า / ลูกค้าไทย จำกัด ตำแหน่ง : วิศวกร shinryo 
 
 
 
 รับผิดชอบ : - การวางแผนความก้าวหน้าของโครงการ 3-weekly รูปร่างแบบ S , ตาราง , รายงานทุกวัน 
 
 
 
 - การควบคุมเอกสาร- ควบคุมโครงการ 
 
 - 
 
 - สัญญาาถอดวัสดุสำหรับโครงการ 
 
 - QA / QC ตรวจสอบเอกสารและรายงานการตรวจสอบความต้านทานฉนวน 
 
 
 
 
 
 &ทดสอบความต่อเนื่องลูปทดสอบ 
 
 - ร้านวาดรูป 
 
 
 
 : บริษัทไรวินท์การบำรุงรักษา& Service Co . , Ltd . 
 
 ตำแหน่ง : วิศวกรไฟฟ้า 
 
 : บริษัทไรวินท์การบำรุงรักษา& Service Co . , Ltd . 
 
 ระยะเวลา : พฤษภาคม 2012 ธ.ค. 
 
 โครงการ :บางป่าในโครงการผลิตไฟฟ้า 1 ( 115kv / การวิเคราะห์คุณภาพการติดตั้งงานไฟฟ้า ) 
 
 ลูกค้า / ลูกค้าไทย shinryo จำกัดตำแหน่ง : วิศวกร electeical 
 
 
 
 หน้าที่ความรับผิดชอบ : - วางแผนโครงการคืบหน้ารูปร่างแบบ S , ตาราง 3-weekly รายวันรายงาน 
 
 - 
 
 - ควบคุมเอกสารโครงการควบคุม 
 
 - 
 
 - สัญญาจัดหาวัสดุ ถอดโครงการ 
 
 - QA / QC ตรวจสอบรายงานและเอกสาร
การแปล กรุณารอสักครู่..
