storage, for immediate use for erection of scaffolding. The dismantled scaffolding material should not
be allowed to pile up in the plant area. Storage facility of scaffold material should be properly
constructed for its stability and load bearing capability. Scaffolding material such as tubes/pipes, planks,
clamps etc. shall be inspected annually to ensure they are free from defects. The visual inspection shall
cover 100% scaffold materials.
Annexure 1: INSPECTION CHECK LIST
S. No
Check Points
Yes/ No/
NA
Remarks
1.
Are the scaffoldings erected as per the load duty requested