The PM also assist the owner in monitoring the Designer's contract costs by preparing a detailed project cost report for all design stages. The report is updated monthly and includes.
-Tracking of designer's actual versus budgeted cost.
-Changes in budget or added items of work for each consultant.
-progress to date in terms of man hours expended and percent complete.
-Estimate of final cost to complete.