Please help to re-visit the comment MTO of instrument Cable because I think the comment not effective please separate original scope and additional scope (During proposal state not confirm approval)
Note If Thai Oil comment mix scope effect to TKIS cannot close the original scope because this document status will open have comment.
By the way if proposal to be award to TKIS, we can re-correct revise MTO during commercial not effect with bidding timeframe and construction requirement.