Example:
1st condition # Column Pick up @ is FTM.
That mean:
1) Supplier will be ship part to FTM by following 862 release order in normal loop, FTM will prepare B500 by FTM self.
2nd condition # Column Pick up @ is Supplier
That mean:
1) In case requirement of each B500 list more than 862 release order.
a. Would supplier control B500 requirement by “Hold” B500 requirement and keep them at supplier plant (No need ship part to FTM).
2) In case requirement of each B500 parts less than 862 release order per day,
a. Would supplier ship part by minus B500 requirement with 862 release order before ship them to FTM every time.
B500 requirement part no. BA61-A513A30-AA is 400 pcs.
862 release order of part no. BA61-A513A30-AA today is 600 pcs.
(862 Release order more than B500 requirement)
That mean supplier must be ship part no. BA61-A513A30-AA q’ty 200 pcs. to FTM