. Thitisak, Pongstorn and NKE team,
Congratulations !! I would like to inform you that, we are selected NKE to contract for Robotic pick&place end cap weld#3,4 project of Emerson Rayong Thailand plant. So I have update RFQ rev 02 please see in qualification plan topic is revised as : If the final qualification did not pass within 8 months supplier will take the machine with all accessories back and will return money that Emerson paid back to Emerson within 15 days.
I would like you consider on this and prepare us for the complete proposal & project contract document before getting sign approval.
Best regards
Sugid