Excavation:
Took 190 days
Had to be done at night
due to strict construction
regulations;
nonetheless, 12,000
cubic meters were
removed each night
Dewatering wells were
installed since the
ground water level was
above the maximum
excavation depth of
24.7m below existing
ground level