Please can you be more accurate
you mention “you think” the item can be relocated.
Please confirm if the relocation you are proposing can be instructed to go ahead.
ผมยืนยันว่าสามารถติดตั้งตามแบบได้
Yes we need to order tile now that correct
For the corridor block B the facade or elevation was to be screening but I was informed by k,Bee that this now has to be blockwork walls so I would like the walls the walls built and rendered before tiling and we will need to look into the corridors having ac and ventilation Khun Noiy will need to look at this and how to fix the condensers to the out side of the walls