management team. The RFMEA technique takes this process further by introducing a third dimension to the risk-ranking matrix, namely, a risk detection score. Using the detection score, a second attribute (the first being the Risk Score) can be calculated for every project risk. This attribute, titled the Risk Priority Number (RPN), in conjunction with the Risk Score, helps improve the identification and prioritisation of critical project risks. The improvements offered by the RFMEA method allow the associated savings in risk management effort to be reallocated to other activities in the project. This increases the likelihood of a successful project outcome and enhances the overall level of productivity within the organisation.