This is regarding OSS notes application to fix the issues in S_P00_07000136.
As explained, around 40 OSS notes need to be applied as per the sequence described in ''Note Sequence'' tab in the attached Excel. Under these 40 OSS notes, some code changes will be applied in multiple transactions, although the code changes will not have impact on functionality of the transactions. You can see in ''Testing Scenarios'' tab in the attached Excel for the transactions to be impacted.
And now I just would like to authorize that the changes can be applied in system (of course we will perform testing in DEV at first and then ask for UAT) by receiving your email confirmation. Can you please give us confirmation that we can proceed to applying the OSS notes ?
(See attached file: 50214 52676 OSS Notes Imp Plan 03 Dec 2015.xls)