Regarding for interference site installation between ELCET, STR, PIPING in “Recovery Phenol Area”, As shown in attached the road has to compressed by site activities then we found crane 25t access to north and attack on pipe underground is damaged along 0.5m approx. deep through pipe surface, So we request to for moving pipe 16”/24m/7 ea to gravel in PHENOL I after site TPM (30/NOV