We conduct first the open-circuit test on the synchronous generator: the generator
is rotated at the rated speed, all the terminals are disconnected from loads, the
field current is set to zero first. Next, the field currentis increased in steps and the
phase voltage (whish is equal to the internal generated voltage EA
since the
armature current is zero) is measured