Dear Mr.Nattapong
Thank you for your kindness,
We pleased to inform you that your work are able to be useful in our new project which is in 304 Industrial Park, Srimahaphot ,Prachinburi.
And we find the company which are professional and high quality for our project.
Would you mind explaining the FREIGHT LIFT 3500 kg. detail more than this drawing mentioned above. Please find attached file,
Anyway,We have some other comments as below,
1.With regard to Schedule for Install Freight lift 3500 kg.,
- 1.1 Please describe your schedule much more than this schedule because we have to know the delivery period of your Materials.
- 1.2 Possible or not that your Machine delivery period will less than 120 days, because our plan to submit you is First of July for order materials and we must keep schedule
which is have to finish work on end of November in worst case.
- 1.3 Possible or not that your installation period will less than this schedule,and possible or not that you will install other mechanical work and electrical work before machine delivery on site.
2.For the drawing,
- 2.1 Please revise your drawing as attached file, please find attached file.
- 2.2 Please revise your level from FL + 00 to above Machine room(Maintenance room) = 10500 mm., because we don't have any space as your requirement.
- 2.3 Pleaserevise your level of First Fl. from FL + 00 to 2FL. we have only 4050 mm., because we don't have any space as your requirement.
- 2.4 Please reduce height size of Machine room(Maintenance room) as attached file, because we don't have any space as your requirement.
- 2.5 Please tell us why you recommend height size of Machine room(Maintenance room) = 3200 mm. , for your maintenance or not ? and can you reduce it.
- 2.6 We still use pit level and change our civill drawing as your recommend = 1200 mm.