Regarding the payment application submission by SBANG dated on 6 Nov 2015 (as attached application)
In reference with the "Term 4" of payment schedule attached in the contract, ABP would like to reject the said application as the work obviously shows it does not achieve the milestone condition specified in the contract (i.e. the concrete slab at 3rd floor is not completed (not pouring yet), as well as the guardhouse progress is not greater than 70%).