Can you prepare a Design Schedule for Key Areas in table format so we know when design of a particular area need to be finalized by operator and top mgmt.
Pls note
• Target of First Presentation is referring to your target date to arrange first presentation to top mgmt/operator, not including those presentation within the working team
• Target of Design Freeze is referring to the date when you supposed to finalize the design so designer can proceed with design development (DD), and the subsequent preparation of submission/tender/for con dwg.
• List only key areas for this table
• This schedule must be in line with your master development schedule where clearly defines when design process shall be ended for next process to start
Pls submit the table in PDF format to K Jum before end of next Monday 3/3/14.
Regards
Heng BC