8.3.1 Inputs to Quality Control
.1 Work results. Work results (described in Section 4.2.3.1) include both process results
and product results. Information about the planned or expected results (from the
project plan) should be available along with information about the actual results.
.2 Quality management plan. The quality management plan is described in Section
8.1.3.1.
.3 Operational definitions. Operational definitions are described in Section 8.1.3.2.
.4 Checklists. Checklists are described in Section 8.1.3.3.