As has demonstrated, proceeding in a forward pass through the network, we can establish the earliest start time and then the earliest finish time for each activity. This process gives the earliest completion time of the entire project, which is the earliest finish time for the last activity. In the case of the shopping centre, the total time required for project completion is 26 weeks.