Learning Curves:
Modularity and increased specialization decreases average
construction cost as more similar vessels are produced.
This is because ship construction labor costs decrease with
experience as build strategy, manufacturing and production
strategy, and management coordinate their efforts with a
more efficient outcome. Therefore the CER's used for the
original vessel have to be modified to take into account
the effects of learning as series of several vessels of the
same class are constructed in sequence.