Upgrading of existing hydraulic control of SKODA turbines into direct
electronic control with Woodward governor PEAK150 including disassembly,
assembly, testing and putting into operation in conformity with the Purchase
Order No. 1001001075 (R1245/16) date May 17, 2016
Signing, i.e. approving this document by both contractual parties, the work “Upgrading of existing
hydraulic control of SKODA turbines into direct electronic control with Woodward governor at Khon
Kaen Sugar Industry Public Company Limited in Thailand” has been satisfactorily completed by
the Supplier and handed over to the Customer in conformity with the Purchase Order No.
1001001075 (R1245/16) date May 7, 2016
Beside of stated above the Invelt Industry International, a.s. also delivered and assembled speed
measurement upgrade for turbines No. 4 and No. 5.