Regarding your capacity survey confirmation sheet for RAP201, you confirmed that can meet our order at peak Qty (include fluctuation +20%)
But actually, KBT's current capacity is only 7900pcs for both 2 P/Ns: Nozzle -0200 and -0250 => NG.
=> Mismatch with capacity confirmed.
By the way, I would like to applogise for making you confused with diffirence between our order by PO and RAP2014.
I updated our forecast Qty for Nozzle -0250 to RAP2014 as below:
So, pls kindly check, re-confirm your capacity and comment countermeasure with adding new Machine schedule, capacity after improvement.
One again, I'm so sorry and hope to receive your support.