A previous formal Management Review meeting was conducted in December 2008 using this minutes template and the agenda on page 1, in line with the requirements of ISO 9001 and MRM procedure QP03.
The minutes from the previous MRM were reviewed and progress note on the majority actions. The following actions were noted as requiring further progression and closure however:
1. Updated Quality Policy to be signed and put on display and on website.
2. A further satisfaction analysis is to be conducted for 2H 2009.
3. Evaluation of compliance to be reviewed in detail as part of Jan 09 environmental auditing (further evaluation included below).