Anyway, please be informed that we are not going to change schedule of
delivery as following.
ETD at port of Nagoya will be on or around October 2, 2015.
ETA at port of Leamchabang will be on or around October 10, 2015.
We will be able to change schedule of commissioning starting around of
end of September to match your schedule of commissioning of extruder as
long as you can match schedule of installation of your extruder to our
annealer.
Please give us instruction of schedule of commissioning.
We will follow to your instruction.
We would like you to find attached information about dispatched
personnel who is Mr. Kazuaki Kamiya, electrical engineer.
We have no preference of hotel at all.
Please pick him up at airport when he arrives Thai.
We also would like you to arrange transportation to airport when he
leaves your country.
You don't have to prepare any kind of tool for commissioning because we
prepare them.
Please give instruction client to prepare tensile tester for sure.
We also would like you to be sure that installation work should be
completed before arrival of our engineer.
Utility installation, water, compressed air and nitrogen, must be
complete before arrival of our engineer.
Particularly, power distribution should be checked at control panel.
We only need three days for commissioning at site.
Please arrange schedule efficiently.
We would like you to remind preparation of materials for commissioning
to client.
We may need three kind of materials one bobbin each.
For example, 0.3 sq mm, 0.5 sq mm and 1.25 sq mm, but any size will be
fine as long as within range of specification.
Should you have further question, please feel free to contact us.
Anyway, please be informed that we are not going to change schedule of delivery as following.ETD at port of Nagoya will be on or around October 2, 2015.ETA at port of Leamchabang will be on or around October 10, 2015.We will be able to change schedule of commissioning starting around of end of September to match your schedule of commissioning of extruder as long as you can match schedule of installation of your extruder to our annealer.Please give us instruction of schedule of commissioning.We will follow to your instruction.We would like you to find attached information about dispatched personnel who is Mr. Kazuaki Kamiya, electrical engineer.We have no preference of hotel at all.Please pick him up at airport when he arrives Thai.We also would like you to arrange transportation to airport when he leaves your country.You don't have to prepare any kind of tool for commissioning because we prepare them.Please give instruction client to prepare tensile tester for sure.We also would like you to be sure that installation work should be completed before arrival of our engineer.Utility installation, water, compressed air and nitrogen, must be complete before arrival of our engineer.Particularly, power distribution should be checked at control panel.We only need three days for commissioning at site.Please arrange schedule efficiently.We would like you to remind preparation of materials for commissioning to client.
We may need three kind of materials one bobbin each.
For example, 0.3 sq mm, 0.5 sq mm and 1.25 sq mm, but any size will be
fine as long as within range of specification.
Should you have further question, please feel free to contact us.