Dear Khun Somporn DA,
Thank you for your cooperation,
- For water supply (TW) and drainage, we will incorporated to M&E drawing and install
install pipe sleeve as per DA information (confirm no future spare)
> confirm no future spare on 3rd floor
- For DI water outlet, we received as information, we are waiting for TREAT details drawing
(Is TREAT received this information ?)
> TREAT has not received yet. We'll send to them by today.
- For power receptacle, we received as information as we understand these are no need floor opening
Or embedded in the slab. And please give more information for the Lab(DA)’s panel which TSMZ need to
supply electrical.
> well noted
- For Electric supply symbol H (+0.30m.), we received as information, as we understand these are DA’s scope and
no need floor opening or embedded in the slab.
> yes
Dear Khun Somporn DA, Thank you for your cooperation,- For water supply (TW) and drainage, we will incorporated to M&E drawing and install install pipe sleeve as per DA information (confirm no future spare) > confirm no future spare on 3rd floor- For DI water outlet, we received as information, we are waiting for TREAT details drawing (Is TREAT received this information ?) > TREAT has not received yet. We'll send to them by today.- For power receptacle, we received as information as we understand these are no need floor openingOr embedded in the slab. And please give more information for the Lab(DA)’s panel which TSMZ need to supply electrical. > well noted- For Electric supply symbol H (+0.30m.), we received as information, as we understand these are DA’s scope and no need floor opening or embedded in the slab. > yes