Firstly, we would highly appreciate your kind comprehension and cooperation towards the removal of protection for the floor and other equipment (LED panel, straps, etc.) in the saloon of all 21 trainsets, whereas the trial running has commenced since this Monday, 13th of May.
The reason we are writing to you today, is to ask you another favor, or human resource support on behalf of J-Trec who is responsible to counter against water leakage in case of rain during this Trial Run. We estimate 36 personnel at maximum for this operation.
As we do need urgently your support, although we are afraid that it might be an abrupt request, your today’s visit to our office in the Depot (the container house in front of OCC building) would be highly appreciated.