Please be noted and advising as follows shipment,
- Supplier Zhejiang Teda Valve Co.,ltd.
1. PO 709008 finished this week (35/2013) Paid Aleady
Fastest Vessel is on Sunday ETD 1 Sep 2013 ** Closed date 30/08/2013
ETA Laem Cha Bang or Bangkok Port 11 Sep 2013
Customs Clearing 2-3 days deliver to our office 13 Sep 2013
** Customer due date is on 30/09/2013 as per PO
** Customer due date is on 20/08/2013 as per PR delay
2. PO 709104 Finished Next Week not paid yet, I’m already send docs to ACD, Krab.
Fastest Vessel is on Sunday ETD 8 Sep 2013 ** Closed date 6/09/2013
ETA Laem Cha Bang or Bangkok Port 18 Sep 2013
Customs Clearing 2-3 days deliver to our office 20 Sep 2013
** Customer due date is on 28/10/2013 as per PO
** Customer due date is on 20/09/2013 as per PR on time.
Please advise what you would like to control these shipments, ship separately or gather shipment. if gather, both of them may be arrived our office on 20 Sep 2013, Krab.