Is it possible to fasten this before the end of JUNE?
If not in that case is it possible to separate and place 2 orders?
1 before the end of this month (where you are sure you're going to run out) and the 2nd on the 8th of JULY (the remaining powers you intend though are not sure to place)?
Why I mention this is that the promised lead time from TOKAI is 1month (4 weeks) for repeat orders.
If by case its placed on the 8th of JULY, I am thinking it could be difficult to ship within JULY especially the 1.60GO.
It will be more easier for production if they can work on the parts of the order (the full order you intend) before the 8th of JULY.
Also it will be easier for me to push production since it's within the 4 month lead time for repeat orders.
I will then work on to add on the order placed on 8th JULY.
Is this possible? Of course the best would be to place all before the end of JUNE though earlier we can start production the earlier the better.