3.5.9 Bay face according to actual installation with printed in color.
3.5.10 As-built drawing printed in color of AutoCAD2000 format on A3 papers.
3.5.11 Internal wiring diagram printed in color of Visio format on A4 papers.
4. Labeling and photos
4.1 Label all hardware equipments and racks according to customer specification
4.2 Label all cables according to customer specification which getting confirmed by customer
4.3 Subcontractor shall send the soft copy of final labeling in excel2003 or MS-Word2003 format to Huawei PM
4.4 Completed photos of site location, including, building sign, room terrain, all hardware equipments, breakers, all wiring cables with mark the interested point, and printed in MS-Word2003 format with color on A4 according to customer specification.
5. Site clearance
5.1 Subcontractor shall cooperate with Huawei engineer and list all remaining hardware materials left after installation into the packing list document with customer signature.
5.2 Subcontractor shall cooperate with Huawei engineer and list all CD-ROM delivered to the site in excel file with customer signature.
5.3. Subcontractor shall clear (dust, etc) and remove all remain materials after installation to designate place (i.e., Customer warehouse). Please study item transportation for more detail.
6. Hardware transportation
6.1 Transportation from Huawei warehouse to the site (ground floor) will be done by Huawei logistics.