Dear ALL,
Regarding the Rebar not Alibaba,PCHP 2 warehouse / Store,we assinged khun Kasidech ( net ) to control receipt and issuing,including stock inventory rebar and all the steel structure,also report the stock remain to construction Dept.of week (monday).
1.The period (27/2/14 to 26/3/14) for rebar reported to Khun Adam by Khun Net calculating unit from pcs. to Kgs.with sheets this period corrected.
2. The period ( 25/3/14 to 26/3/14 ) for rebar reported to Khun Adam by Khun Net calculating unit from pcs. to KGS.with Khun Onchaporn ( Suthee control ) last rebar sheets send to k.Adam by K.Onchaporn.on 25/3/14
all MISTAKE.not only the rebar,have other steel.
Our responsibilities.
Best Regards,