If the Supplier suffers delay and/or incurs Cost from complying with the Owner’s instructions under Sub Clause 8.8 (Suspension of Works) and/or from resuming the work, the Supplier shall give notice to the Owner and shall be entitled subject to Sub Clause 20.1 (Supplier’s Claims) to:
(A) an extension of time for any such delay, if completion is or will be delayed, under Sub Clause 8.4 (Extension of Time for Completion), and
(B) if any such delay exceeds 90 days, payment of any Costs incurred after the 90 days by reason of such delay, which shall be added to the Contract Price.
After receiving this notice, the Owner shall proceed in accordance with Sub Clause 3.5 (Determinations) to agree or determine these matters.
The Supplier shall not be entitled to any extension of the Time for Completion or to payment of the Cost incurred in making good the consequences of the Supplier’s faulty design, workmanship or materials, or of the Supplier’s failure to protect, store or secure in accordance with Sub Clause 8.8 (Suspension of Works).
The aggregate amount added to the Contract Price or otherwise paid under this Sub-Clause shall not exceed 5% of the Contract Price.