It was assumed that the biorefinery is located in Germany on an existing chemical site, at which all required utilities and waste water treatment can be provided. A capacity to process 400,000 dry tonnes of beech wood annually was found to be reasonable (Michels, 2009). The plant operates 8000 h per year. The remaining 760 h are for maintenance, repair and restarting the operations.