Dear Mr. Xu
I do not agree to start the piling work tomorrow due to incompletion of piling design drawing and conflict of MR GA and Plot plan drawing will need to be resolved to finalize the piling plan.
In addition there are number of documents which are not submitted for review and approval i.e. Pile drawing and calculation, Piling Procedure, blow count calculation and final location of outlet pipe support to Power plant. Not sure if Pile rig has been inspected before utilization if not so please do it.
Please urgently clarify and submit all of these outstanding documents prior to we can allow you to start.