Project2013 introduces a feature called TaskPath that applies color formatting to the Ganttbars of the selected task’s predecessorr tasks and successorr tasks .
TaskPath can also distinguish a task’s driving predecessor (the predecessor that directly determines, or drives, the start date of the task) from that task’s other predecessors