Article 3
The term "the Project Manager" in the Contract shall mean the said Representative of Vattanac
Properties Limited or, in the event of his ceasing to be the Project Manager for the purpose of the
Contract, such other person as the Employer shall appoint within twenty eight (28) days therefrom.
No Project Manager so appointed shall be entitled to disregard or overrule any certificate or opinion
or decision or approval or instruction given by the preceding Project Manager.
The Project Manager may from time to time delegate his duties and authority to the Quantity
Surveyor, the Resident Supervisor or other consultants as he deemed fit.