Points discussed on meeting:
- Dust protection should be delivered, installed and dismounted in the existing Paint Shop FTM Rayong
- The dust protection must avoid that dirt or dust can reach the production bodies
- The execution must be strong and not easy to destroy by normal touching
- Dust protection existing of several material for several areas:
o Sheet metal, corrugated metal wall including supporting elements if necessary
o Foil including supporting elements if necessary
o Doors in sheet metal with door frames / Quantity of total doors must be given for Steel Doors
o Quantity of fire blanked doors will be defined during installation and are included in total contract cost
- All material used must be silicone free and approved by DÜRR / FORD before purchased.
Sample has to be provided.
- Openings for pipes, ducts cable trays, steel structures same like other interferences need to be done and sealed during installation and are included in total total contract cost
- All openings in the dust protection area must be closed, especially all the interface to building and equipment
- Basis for the scope are the layouts for all levels
- Additionally steel work drawing will be hand over to subcontractors before start of installation
- Installation and dismantle is include price, there are 2 options for material
o 1st “ Rental based” stay with subcontractor after dismantle / rental option
Subcontractor has to consider material will be partly damaged and cannot be back charged to Dürr
o 2nd “Purchase based” material purchased by Dürr include price
- In case some additional opening needs to be done which could not be foreseen earlier, Dürr will request subcontractor to come to site. Cost is included to total price.
- In case part of the wall damaged / penetrated by others, subcontractor has to come to site to do repair asap. Additional cost will be paid by Dürr.
- Subcontractor has to follow Dürr / Ford and Local Safety Regulation
- Job safety plan needs to be prepared by subcontractor before job starts and needs to be approved by Dürr / Ford
- Installation during production must done careful, without interface to running body production
- Mean installation is planned during production stop
- General concept drawings need to be provided by subcontractors and approved by Dürr / Ford before start
- Clamping to existing structures is possible, subcontractor has to avoid damaged while clamping. By using wood for example
Please attached find discussed solutions for PT/ED and UBS Oven.
If you will have any question, or in case of any comments don´t hesitate to contact me.
Thanks.
Points discussed on meeting:
- Dust protection should be delivered, installed and dismounted in the existing Paint Shop FTM Rayong
- The dust protection must avoid that dirt or dust can reach the production bodies
- The execution must be strong and not easy to destroy by normal touching
- Dust protection existing of several material for several areas:
o Sheet metal, corrugated metal wall including supporting elements if necessary
o Foil including supporting elements if necessary
o Doors in sheet metal with door frames / Quantity of total doors must be given for Steel Doors
o Quantity of fire blanked doors will be defined during installation and are included in total contract cost
- All material used must be silicone free and approved by DÜRR / FORD before purchased.
Sample has to be provided.
- Openings for pipes, ducts cable trays, steel structures same like other interferences need to be done and sealed during installation and are included in total total contract cost
- All openings in the dust protection area must be closed, especially all the interface to building and equipment
- Basis for the scope are the layouts for all levels
- Additionally steel work drawing will be hand over to subcontractors before start of installation
- Installation and dismantle is include price, there are 2 options for material
o 1st “ Rental based” stay with subcontractor after dismantle / rental option
Subcontractor has to consider material will be partly damaged and cannot be back charged to Dürr
o 2nd “Purchase based” material purchased by Dürr include price
- In case some additional opening needs to be done which could not be foreseen earlier, Dürr will request subcontractor to come to site. Cost is included to total price.
- In case part of the wall damaged / penetrated by others, subcontractor has to come to site to do repair asap. Additional cost will be paid by Dürr.
- Subcontractor has to follow Dürr / Ford and Local Safety Regulation
- Job safety plan needs to be prepared by subcontractor before job starts and needs to be approved by Dürr / Ford
- Installation during production must done careful, without interface to running body production
- Mean installation is planned during production stop
- General concept drawings need to be provided by subcontractors and approved by Dürr / Ford before start
- Clamping to existing structures is possible, subcontractor has to avoid damaged while clamping. By using wood for example
Please attached find discussed solutions for PT/ED and UBS Oven.
If you will have any question, or in case of any comments don´t hesitate to contact me.
Thanks.