Seller shall not, without Buyer’s prior written consent, manufacture or procure materials in advance of Seller’s normal and reasonable flow time in order to meet the Agreement Schedule. In the event of Termination For Convenience or Change, no claim will be allowed for any such manufacturing or procurement in advance of such normal flow time unless there has been prior written consent from Buyer.