During market survey, Agent had checked with CAT workshop and Chaiwat Workshop in Thailand but both WQT workshop did not have WQT pipe that suitable for Project ready and has to make a new purchase that will not be on-time and also pricing was almost double.
After evaluation from timeline and commercial, found Piyanan Workshop is the most suitable to meet Project requirement.
I have attached minute of meeting between Piyanan Workshop and Agent on Saturday, 20th Jun and demand to receive payment cheque by this Friday, 26 Jun.
Please assist to make a payment by this Friday, 26 Jun that already 3 months from invoice submission.