The overtopping resulted in:
Cracking of the concrete in the upstream monoliths
Cracking at the dam-foundation interface
Seepage through the dam was 18.4 cms and through the foundation 19.4 cms
In response to these problems the cracking was grouted and a decision was made to reduce the normal water level 1 meter.