We got confirmation detail as below,
1. Anchor bolts for embedded in the Alstom foundation area: They will be delivered to site with shipment #1; Lot 2 of 3 on 17-Oct-15.
2. Anchor bolts for embedded in remaining foundation area , Hold Down straps, Rubber neoprene pads and Coating and Wrap tap for field welding: They will be delivered to site with shipment #1; Lot 3 of 3 on 31-Oct-15.