Check Stage
When the final issue closed, all results from the new procedures were gathered and reviewed. The focus was on identifying net improvement for each milestone event. In addition, any impact upon the overall process completion time was studied. Sometimes individual events can show improvement, but the overall process can remain the same. If a redesigned part runs into a production delay, for example, the entire RFF process can get a negative rating. Fortunately, the detailed milestone calendar accurately shows the performance of the changes implemented and effects from unavoidable delays can be isolated