I acknowledged your instruction below massage.
I make schedule plan and follow plan as below.
1. Damage Pallet : separate which one can repair and which one need to sale out.
Action plan:
• Separate within 21 Jan 2016.
• Contact supplier for quotation repair 18-22 Jan 2016.
• Repairing damage pallet within 31 Jan 2016.
2. We no need to keep some desk or some material damage. Please clear it.
Action plan:
• Checking some desk and material damage 18-19 Jan 2016.
• Corporate information admin about selling to scrap 20-21 Jan 2016.
• Sale scraps within 21 Jan 2016.
3. Please ask supplier come to check one of F/L were move from LCB problem about battery before make big trouble.
Action plan:
• Contact supplier checking battery and issue report result after checking and quotation within 25 Jan 2016.
4. Corporate with SPCT about maximum wooden pallet we can keep in our WH back side. And as you see, the condition of pallet is not so good with can bring some of white ant come to inside WH which we should consider.
Action plan:
• Report stock empty pallet to SPCT already 16 Jan2016.
• Make maximum kept empty pallet offer SPCT within 17 Jan 2016.
• Concluding volume with SPCT within 23 Jan 2016.
5. JX-Loscam pallet, how many unit should be keep for support our process of preparing.
Action plan:
• Report stock empty pallet to JX on 18 Jan 2016.
• Make maximum kept empty pallet Loscam offer JX within 19 Jan 2016.
• Concluding volume with JX within 23 Jan 2016.
6. Please announce to our staff keep some gap between wall when they put cargo, pallet or any.
Action plan:
• Announce to rule to all staff on 19 Jan 2016.
• Re-arrange some pallet kept closed wall within 23 Jan 2016.
7. Find supplier to make a steel plate for cover gutter replace old one damage.
Action plan:
• Find suppliers issue quotation with comparing cost within 31 Jan 2016.